How long will it take?

Pick a project. This is the shape of the schedule you get before you sign anything.

15 weeks from signing to handover

  1. Design and order

    Weeks 1 to 5

    Drawings, permit and cabinets on order. You still have a kitchen.

  2. Demolition

    Week 6

    Down to the studs. A temporary sink goes in another room.

  3. Rough-in

    Weeks 7 to 8

    Plumbing, wiring and ducts moved, then inspected.

  4. Walls and floor

    Weeks 9 to 10

    Drywall, primer and the new floor.

  5. Cabinets and counters

    Weeks 11 to 13

    Cabinets set, counters templated and installed.

  6. Finish

    Weeks 14 to 15

    Tile, paint, appliances, lighting and the punch list.

Sample durations for this concept. The grey bar is planning: nothing in your house has been touched yet.