How long will it take?
Pick a project. This is the shape of the schedule you get before you sign anything.
15 weeks from signing to handover
Design and order
Weeks 1 to 5Drawings, permit and cabinets on order. You still have a kitchen.
Demolition
Week 6Down to the studs. A temporary sink goes in another room.
Rough-in
Weeks 7 to 8Plumbing, wiring and ducts moved, then inspected.
Walls and floor
Weeks 9 to 10Drywall, primer and the new floor.
Cabinets and counters
Weeks 11 to 13Cabinets set, counters templated and installed.
Finish
Weeks 14 to 15Tile, paint, appliances, lighting and the punch list.
Sample durations for this concept. The grey bar is planning: nothing in your house has been touched yet.